We are working with Michigan Paving to begin laying asphalt on Seymour Road and Trist Road, between Elm Road and Clear Lake Road, beginning Wednesday, July 19, 2017, weather permitting.
Work is expected to be completed in three weeks, on this 14 mile stretch of road.
Flaggers will be directing traffic. No detour route will be posted, and motorists should expect short delays.
Paving in Sandstone Township
Construction will begin next week, when crews start paving the entire length of both Leora Lane and Cuff Road on Monday, July 24, 2017, weather permitting. Additional work will include laying gravel shoulders and is expected to be completed in one week.
Flaggers will be directing traffic. No detour route will be posted, and motorists should expect short delays.